HOUSTON - NextDecade (NASDAQ:NEXT) Corporation (NASDAQ: NEXT) has announced consistent advancement in the construction of its Rio Grande LNG project's Phase 1, maintaining alignment with the scheduled timeline and budget. According to a recent statement, the overall project completion for Trains 1 and 2, along with the common facilities, has reached 30.5% by September 2024, with engineering, procurement, and construction components making significant headway.
The company's Chairman and CEO, Matt Schatzman, highlighted the substantial progress made in the past few months, with Bechtel Energy Inc. overseeing the construction efforts. Schatzman emphasized the prioritization of safety and risk management throughout the project's development.
Strategic and commercial milestones include the appointment of Tarik Skeik as Chief Operating Officer in July 2024, bringing over two decades of experience in global mega project delivery. Additionally, NextDecade entered into an EPC contract with Bechtel for Train 4 and its infrastructure in August 2024, with price validity extending through the end of the year.
The project faced a regulatory setback when the U.S. Court of Appeals for the D.C. Circuit vacated the Federal Energy Regulatory Commission's reauthorization of the facility in August 2024. However, NextDecade filed a petition for rehearing in October, and construction continues while the appeals process is underway.
NextDecade is focused on achieving a positive final investment decision (FID) for Trains 4 and 5, contingent on maintaining government approvals, finalizing commercial arrangements, and securing adequate financing. The company has made progress in commercial discussions, including an LNG sales and purchase agreement with ADNOC and a heads of agreement with Aramco for Train 4, with further negotiations expected to finalize binding agreements.
The Rio Grande LNG Facility is a key project for NextDecade, expected to have a significant capacity for LNG production and export upon completion. The facility's strategic location on the Brownsville Ship Channel in south Texas includes extensive frontage and infrastructure designed to support the operation of up to five trains.
The information provided is based on a press release statement from NextDecade Corporation.
In other recent news, NextDecade Corporation has seen significant changes in its board and operations. Arnaud Lenail-Chouteau, a seasoned professional from TotalEnergies (EPA:TTEF), has been appointed as a Class A director, filling the vacancy left by Thibaud de Préval. The company has also secured a $4.3 billion contract with Bechtel Energy for the addition of a fourth liquefaction train at the Rio Grande LNG facility. In addition, Tarik Skeik has been appointed as the new Chief Operating Officer.
NextDecade has withdrawn its application for a carbon capture and storage (CCS) project at the Rio Grande LNG facility due to insufficient development. However, the company remains committed to advancing CCS technology. Analyst sentiment is divided, with Stifel maintaining a Buy rating for NextDecade, while TD Cowen retains a Hold rating.
The company has made progress with its Rio Grande LNG project, securing a head of agreement with Saudi Aramco (TADAWUL:2222) for 1.2 million tonnes per annum for Train 4 of the project. This follows a contract with Abu Dhabi National Oil Company (ADNOC), which also acquired an 11.7% equity stake in the first phase of the project. These are recent developments in the company's operations.
InvestingPro Insights
NextDecade Corporation's (NASDAQ: NEXT) ambitious Rio Grande LNG project is progressing amid a complex financial landscape. According to InvestingPro data, the company's market capitalization stands at $1.8 billion, reflecting investor interest in its potential. However, the road ahead appears challenging, as evidenced by several key metrics.
InvestingPro Tips highlight that NextDecade is "quickly burning through cash" and "operates with a significant debt burden." These factors are particularly relevant given the capital-intensive nature of LNG projects and the company's focus on achieving a positive final investment decision for additional trains. The tip indicating that "short-term obligations exceed liquid assets" further underscores the financial pressures the company may face as it pushes forward with construction.
Despite these challenges, the market seems optimistic about NextDecade's prospects. The stock has shown a "significant return over the last week" and a "strong return over the last month," with a 34.77% price total return over the past month. This positive momentum aligns with the project's reported progress and strategic milestones.
It's worth noting that analysts do not anticipate the company to be profitable this year, which is consistent with the negative EBITDA of -$144.84 million for the last twelve months as of Q2 2024. This reflects the current investment phase of the Rio Grande LNG project.
For investors seeking a more comprehensive analysis, InvestingPro offers additional tips and insights that could provide a fuller picture of NextDecade's financial health and market position. Currently, there are 8 additional InvestingPro Tips available for NEXT, which could offer valuable context for understanding the company's trajectory as it navigates the complex landscape of LNG development.